Removing the hold on a scheduled job

When you remove the hold on a scheduled job, the job then runs according to the schedule.

To remove the hold on a scheduled job

  1. On the navigation bar, click Job Monitor.

  2. On the Job List tab, in the Current Jobs pane, select the scheduled job.

    To select multiple jobs, select a job, and then press the <Ctrl> or <Shift> keys while you click other jobs that you want to select. This allows you to remove the hold from more than one job at a time, as long as the state of the jobs are the same.

  3. In the task pane, under General Tasks, uncheck Hold Schedule.

Removing the hold on a scheduled job